Vehicle Crossings in Auckland (2026): Approval, Cost and Who Pays

sp8002
Oct 29
7 min read

Updated: 5 days ago

Short answer. In Auckland the property owner pays to build, repair and maintain the vehicle crossing: the part of the driveway between your boundary and the road. It sits in the road reserve, so every repair, rebuild, widening or removal needs written approval first. Since 1 October 2026 Auckland Council approves it (Auckland Transport did before). The fee is $546 including GST and covers three inspections. Allow about 20 working days for approval.

Updated 4 November 2026.

What changed on 1 October 2026, and what didn't

Auckland Council became the road controlling authority on 1 October 2026. Auckland Transport now runs public transport only.

For vehicle crossings, very little moved on day one:

  • Applications are still lodged on the AT website's Road Services portal, through a MyAT account.

  • Corridor access requests still run on MyWorksites.

  • The fee is invoiced by Auckland Council.

  • The phone number is still 09 355 3553.

  • The standards are the same documents: the Transport Design Manual vehicle crossing drawings and Unitary Plan chapter E27.

Inspectors and approval letters may still carry AT names and numbers for a while. That is normal during the handover.

If you searched "AT vehicle crossing" or "Auckland Transport vehicle crossing permit", this is the same process.

Is it your crossing, or your driveway?

Check this before you price anything. The crossing starts at your front boundary, usually the line of your front fence or boundary pegs. Everything on the street side of that line is road reserve: the crossing, the footpath, the berm, the kerb. The part of the drive inside your boundary is private, and repairing it needs no council approval.

We learned to check this on site. On a Glenfield body corporate job this year, the broken section at the entrance looked like the crossing in photos. On site, it turned out to be driveway inside the boundary. No permit, no inspection, and a simpler job. Measure from the boundary pegs, not from the photo.

Who pays: owner, council, or whoever damaged it

  • Crossing cracked, sunk or broken with age: property owner. The owner builds and maintains the crossing.

  • You want it wider, moved or a second one: property owner. It needs a new approval and possibly resource consent.

  • Old crossing no longer needed (e.g. after a rebuild): property owner. Kerb, footpath and berm go back to standard.

  • Council widens or realigns the road: council. This is the only council-paid case in the rules.

  • A utility contractor damaged it: the utility. Utility work is warranted for 2 years.

  • A builder next door or a delivery truck damaged it: whoever caused it, recovered by the owner. Council pursues builders through street damage inspections; for trucks it's a civil claim.

  • Council says it's unsafe: property owner. Council can order the repair and charge you if it does the work.

The council fixes footpaths, kerbs and channels. It does not fix a privately owned crossing for free. More on berm and crossing damage.

How approval works, step by step

  1. Check what's needed. Resource consent comes first if the crossing will be wider than 3 m at the boundary, within 3 m of a street tree, within 10 m of an intersection, or on an arterial road frontage.

  2. Apply on the Road Services portal with a scaled site plan, the crossing location, site photos and photos of street features nearby (poles, pits, trees, signs).

  3. Pay $546 incl GST. Auckland Council emails the invoice.

  4. Pre-approval inspection. The road corridor inspector checks the site: sight lines, gradients, stormwater, trees and utilities. They also set the traffic management level.

  5. Approval letter, targeted within 20 working days. It sets the specification and any conditions. No work before this letter.

  6. Excavate and box, with a traffic and pedestrian management plan in place for the whole job, including any open hole overnight.

  7. Pre-pour (boxing) inspection. Book with 2 working days' notice. Pour within 7 days of passing.

  8. Pour, saw-cut, topsoil and seed the berm.

  9. Final inspection. Book with 2 working days' notice. A pass gives a certificate of completion, and a copy goes on your property file.

Build without approval and the council can make you remove or redo it at your cost. An unauthorised crossing can also show up on a LIM.

What a standard Auckland crossing looks like

  • Width: 3.0 m at the boundary and 6.2 m at the kerb for a standard residential crossing. Single-house crossings are 2.75–3.0 m at the boundary. Wider needs resource consent.

  • Concrete: 150 mm of 20 MPa concrete on 100 mm compacted GAP40. It's unreinforced unless it serves 4 or more homes (then 665 mesh). Ten or more homes, or heavy vehicles, need the commercial standard: 200 mm with 661 mesh.

  • Material and level: the crossing must match the footpath's level, colour and material, because pedestrians have priority.

  • Gradient: residential drives no steeper than 1 in 5, with a flatter platform where the drive meets the road.

  • Spacing: one crossing per 25 m of frontage, 6 m apart on the same site.

A typical residential crossing covers 12–20 m², depending on berm depth.

Most crossings are concrete and asphalt

This part catches people out. When the old crossing comes out, the kerb and channel often go with it. If the channel is replaced, the standard drawings require a strip of road to be reinstated as well: at least 1 m of road along the crossing, in hot-mix asphalt at least 40 mm thick and matched to the existing road depth.

So a "concrete job" usually ends with an asphalt road edge. Some streets have asphalt footpaths, and there the crossing can be asphalt too: 25 mm Mix 10 on 300 mm GAP40. Concrete-footpath streets get concrete crossings.

We do both surfaces: one quote, one contact and one set of inspections. You don't have to coordinate a concreter and an asphalt contractor around a council inspector. See concrete driveway repair and footpath and road reinstatement.

What it costs (2026, excluding GST)

  • Council vehicle crossing fee (includes 3 inspections): $546 incl GST, fixed

  • Seal cracks / patch one area (still needs approval): $300–$800

  • Replace one broken panel: $300–$500 per m², minimum about $1,500

  • Full rebuild of a 12–20 m² residential crossing, incl. road-edge asphalt strip: $5,500–$8,500

  • Traffic management on a busy or arterial road: from about $850 per day

  • Asphalt road strip only (after someone else's concrete): from $1,075

What moves the price:

  • berm depth (more m²);

  • an arterial road (traffic management);

  • a stormwater pit or manhole in the splay;

  • basalt kerb blocks to salvage;

  • exposed-aggregate or coloured footpaths to match.

You get a price range the same business day from photos, then a fixed price after a free site measure.

How long it takes

  • Approval: up to about 20 working days.

  • On site: 1–3 days once the boxing inspection is booked (2 working days' notice).

  • Before you drive on it: our concrete is usually ready for cars in 5–7 days. That is our practice, not a council rule. Council's own footpath standard keeps new footpath concrete free of wheels for 28 days, so ask us what your mix allows.

Can't be without your car? Tell us early. Where the crossing is wide enough, we can do one half at a time.

Who builds it

You can use any competent contractor. There is no council "approved crossing contractor" list. The owner (or an agent such as your builder or contractor) applies, and must give the contractor a copy of the approval and its conditions.

We price and build the crossing, the footpath edge and the road strip together, to the conditions in your approval letter. Need a hand with the application? Ask when you send photos. Developers: a crossing still needs its own vehicle crossing approval unless it's part of your subdivision consent.

Cracks in the driveway behind the crossing? See concrete crack repair in Auckland for which cracks matter and what they cost.

Building a new driveway behind the crossing? See new concrete driveway cost in Auckland.

Frequently asked questions

What is a vehicle crossing?

The part of your driveway between the road and your property boundary, where cars cross the footpath and berm. It sits in the road reserve, so the council controls how it's built, but the property owner pays for it.

Do I need permission to repair my vehicle crossing in Auckland?

Yes. Building, widening, moving, removing or repairing a crossing all need written approval from Auckland Council before work starts. The application is still lodged on the AT Road Services portal during the handover.

How much is the vehicle crossing application fee?

$546 including GST, from 1 July 2026. It's fixed and covers the pre-approval, pre-pour and final inspections.

How long does vehicle crossing approval take?

The council targets 20 working days for the approval letter. Then each inspection needs 2 working days' notice.

Is it Auckland Transport or Auckland Council now?

Auckland Council, since 1 October 2026. AT runs public transport only. The crossing forms and portal are still on the AT website during the handover.

Who pays to fix a vehicle crossing in Auckland?

The property owner, unless someone else damaged it. Council pays only when its own road works force a change.

Can I widen or move my driveway entrance?

Yes, with a new approval. Wider than 3 m at the boundary, or close to a tree or intersection, needs resource consent first. The old crossing then has to be reinstated as kerb, footpath and berm, at your cost.

Can a vehicle crossing be asphalt?

Yes, where the footpath is asphalt. The crossing has to match the footpath. Concrete-footpath streets get concrete crossings.

Does replacing a crossing mean road works too?

Often. If the channel is replaced, the standard needs an asphalt strip of road reinstated, at least 1 m wide.

Does Rapidpatch build and repair vehicle crossings?

Yes. Rapidpatch repairs and rebuilds vehicle crossings across Auckland, in concrete and asphalt, including the footpath edge, kerb and the road strip. Send photos of the crossing and the kerb for a price range the same business day.

Crossing cracked, failed an inspection, or need a new one? Send photos of the crossing and the kerb, plus the address. You get a price range the same business day. Or call 027 737 2858.

 
 
 