The A9 Works Completion Notice, Explained for Auckland Drainlayers and Builders
Updated: Nov 5
The A9 is the works completion notice under the National Code of Practice for Utility Operators' Access to Transport Corridors. When your work in the road reserve is finished, the holder of the corridor access approval (the CAR holder) lodges it to tell the corridor manager that the job is complete and reinstated to standard. In Auckland the corridor manager is now Auckland Council (Auckland Transport until 1 October 2026).
If you're a drainlayer or builder doing one connection a month, the A9 is easy to forget, and it's often the reason a job isn't closed out. Here's what goes in it.
Who fills it in and who lodges it
The CAR holder signs and lodges the notice. The contractor who did the reinstatement normally fills in the details and supplies the attachments, because they hold the measurements, photos and test results. Lodge it promptly once the work is done. Your approval conditions set the deadline, and 10 working days is common.
What to attach
A sketch of the extent and location of the reinstatement: road, footpath, crossing, with dimensions.
Photos before, during and after, including the base before surfacing.
Compaction test results for road reinstatements, usually nuclear density meter readings against the material's maximum dry density.
Materials: the asphalt mix (AC14 is typical for Auckland road edges) and concrete details where relevant.
The CAR or WAP number and the dates the work was done.
Mistakes that hold up sign-off
No compaction results, or results taken on the wrong layer.
A sketch that doesn't match what the inspector sees on site, usually because the marked-out area grew and nobody updated the drawing.
Footpath patched instead of replaced panel to panel.
Lodging late, after the approval has expired.
After you lodge it
The corridor manager may inspect before accepting the work. Once it's accepted, the maintenance period starts, commonly two years for reinstatements. Defects that show up in that time come back to the CAR holder, so keep the A9 pack and the photos.
How Rapidpatch handles it
Rapidpatch reinstates the whole strip from your boundary to the road, concrete and asphalt, under one contractor. We work to your CAR's hold points and give you the photos, measurements and records for your A9, ready for you to complete and lodge. If your CAR needs a compaction test, ask us to price it in. See trench, footpath and road reinstatement.
Frequently asked questions
What is an A9 form?
The works completion notice under the National Code of Practice for Utility Operators' Access to Transport Corridors. The CAR holder lodges it when work in the road reserve is finished and reinstated.
Who signs the A9?
The holder of the corridor access approval. Their contractor usually prepares it and supplies the attachments.
Do I need compaction tests for the A9?
For road reinstatements, inspectors usually ask for basecourse compaction results. Get the test done before the asphalt goes down.
When does the maintenance period start?
When the corridor manager accepts the completed work. It is commonly two years for reinstatements.
Need the reinstatement and the A9 pack done together? Send the CAR number and photos. 027 737 2858